Construction of the new Liberty development is underway! We broke ground earlier this year and have been making great progress preserving the history of the area while updating modern utilities. We wanted to share our progress with you.

 

Fun Facts About the Construction Progress

 

  • 200+ workers on site every day
  • 6-8 earth moving and utility crews on site
  • 1 mile of storm sewer pipe installed
  • 1 mile of sanitary sewer pipe installed
  • 1.5 miles of water line installed
  • Over 2 miles of new sidewalk and trails to be built
  • Over 100,000 original bricks re-used for walkways, courtyards and building restoration
  • Over 60,000 cubic yards of dirt moved to date
  • 22.3 acres of ground graded
  • 9,850 feet of new curb and gutter to be placed
  • Over 500 new trees will be planted
  • 8 acres of soil amended to reduce stormwater runoff
  • Over 6 acres placed in conservation easement